143,540 judgment pages 132,515 public-register pages 276,055 total pages

JOHN LOUIS v LEONARD MCLAULDY

2007-08-13 · Saint Lucia · Claim No. SLUHCV 2004/0516
Metadata
Collection
High Court
Country
Saint Lucia
Case number
Claim No. SLUHCV 2004/0516
Judge
Key terms
Upstream post
7730
AKN IRI
/akn/ecsc/lc/hc/2007/judgment/sluhcv-2004-0516/post-7730
PDF versions
  • 7730-13.08.07johnlouisvleomclauldy.pdf current
    2026-06-21 03:11:01.114374+00 · 12,410 B

Text

PDF: 1,872 chars / 306 words. WordPress: 1,874 chars / 307 words. Word overlap: 97.0%. Length ratio: 0.9989. Audit: minor content delta (medium). Token overlap: 99.0%.

IN THE EASTERN CARIBBEAN SUPREME COURT IN THE HIGH COURT OF JUSTICE (CIVIL) SAINT LUCIA CLAIM NO. SLUHCV2004/0516 BETWEEN: JOHN LOUIS Claimant and LEONARD MCLAULDY Defendant Appearances : Mr. S. John for Claimant Mr. K. Monplaisir Q.C. for Defendant ________________________ 2007: April 18; August 13. ________________________ RULING

[1]This is an application by the Claimant for assessment of damages. When the matter came up for hearing on April 18th, 2007 it was adjourned pending receipt of the written submissions on that assessment by the Defendant’s Counsel.

[2]Upon receipt of those submissions and on a perusal of the entire file, it appears that the application by the Claimant cannot be granted. When this matter came before Shanks J. on February 3 rd, 2005 the parties reported to the Court that they had reached agreement. Counsel for both sides undertook to lodge an agreed Order. The agreed Order was never lodged.

[3]The matter came up before Shanks J. on June 22nd, 2005. Realizing that no order had been lodged, the Judge reduced the agreement of the parties to a Court Order which the Court Office produced. Under that Order the Defendant was to carry out certain works.

[4]The Claimant considered that the works were not carried out in accordance with the Court Order and applied to have the Defendant committed for contempt. Eventually the works were completed and the Court appointed engineer has certified that the works conform to the Order of the Court.

[5]The Claimant now applies to have his damages assessed. Unfortunately there has never been any judgment entered for the Claimant for damages to be assessed.

[6]The Claimant’s application is thus dismissed as wholly misconceived.

[7]I award the Defendant his costs on this application which I assess in the amount of $750.00. _________________________ BRIAN S. COTTLE HIGH COURT JUDGE

IN THE EASTERN CARIBBEAN SUPREME COURT IN THE HIGH COURT OF JUSTICE (CIVIL) SAINT LUCIA CLAIM NO. SLUHCV2004/0516 BETWEEN: JOHN LOUIS Claimant and LEONARD MCLAULDY Defendant Appearances : Mr. S. John for Claimant Mr. K. Monplaisir Q.C. for Defendant ________________________ 2007: April 18; August 13. ________________________ RULING

[1]This is an application by the Claimant for assessment of damages. When the matter came up for hearing on April 18th,

[2]Upon receipt of those submissions and on a perusal of the entire file, it appears that the application by the Claimant cannot be granted. When this matter came before Shanks J. on February 32007 it was adjourned pending receipt of the written submissions on that assessment by the Defendant’s Counsel. rd, 2005 the parties reported to the Court that they had reached agreement. Counsel for both sides undertook to lodge an agreed Order. The agreed Order was never lodged.

[3]The matter came up before Shanks J. on June 22nd, 2005. Realizing that no order had been lodged, the Judge reduced the agreement of the parties to a Court Order which the Court Office produced. Under that Order the Defendant was to carry out certain works.

[4]The Claimant considered that the works were not carried out in accordance with the Court Order and applied to have the Defendant committed for contempt. Eventually the works were completed and the Court appointed engineer has certified that the works conform to the Order of the Court.

[5]The Claimant now applies to have his damages assessed. Unfortunately there has never been any judgment entered for the Claimant for damages to be assessed.

[6]The Claimant’s application is thus dismissed as wholly misconceived.

[7]I award the Defendant his costs on this application which I assess in the amount of $750.00. _________________________ BRIAN S. COTTLE HIGH COURT JUDGE

PDF extraction

IN THE EASTERN CARIBBEAN SUPREME COURT IN THE HIGH COURT OF JUSTICE (CIVIL) SAINT LUCIA CLAIM NO. SLUHCV2004/0516 BETWEEN: JOHN LOUIS Claimant and LEONARD MCLAULDY Defendant Appearances : Mr. S. John for Claimant Mr. K. Monplaisir Q.C. for Defendant ________________________ 2007: April 18; August 13. ________________________ RULING

[1]This is an application by the Claimant for assessment of damages. When the matter came up for hearing on April 18th, 2007 it was adjourned pending receipt of the written submissions on that assessment by the Defendant’s Counsel.

[2]Upon receipt of those submissions and on a perusal of the entire file, it appears that the application by the Claimant cannot be granted. When this matter came before Shanks J. on February 3 rd, 2005 the parties reported to the Court that they had reached agreement. Counsel for both sides undertook to lodge an agreed Order. The agreed Order was never lodged.

[3]The matter came up before Shanks J. on June 22nd, 2005. Realizing that no order had been lodged, the Judge reduced the agreement of the parties to a Court Order which the Court Office produced. Under that Order the Defendant was to carry out certain works.

[4]The Claimant considered that the works were not carried out in accordance with the Court Order and applied to have the Defendant committed for contempt. Eventually the works were completed and the Court appointed engineer has certified that the works conform to the Order of the Court.

[5]The Claimant now applies to have his damages assessed. Unfortunately there has never been any judgment entered for the Claimant for damages to be assessed.

[6]The Claimant’s application is thus dismissed as wholly misconceived.

[7]I award the Defendant his costs on this application which I assess in the amount of $750.00. _________________________ BRIAN S. COTTLE HIGH COURT JUDGE

WordPress

IN THE EASTERN CARIBBEAN SUPREME COURT IN THE HIGH COURT OF JUSTICE (CIVIL) SAINT LUCIA CLAIM NO. SLUHCV2004/0516 BETWEEN: JOHN LOUIS Claimant and LEONARD MCLAULDY Defendant Appearances : Mr. S. John for Claimant Mr. K. Monplaisir Q.C. for Defendant ________________________ 2007: April 18; August 13. ________________________ RULING

[1]This is an application by the Claimant for assessment of damages. When the matter came up for hearing on April 18th,

[2]Upon receipt of those submissions and on a perusal of the entire file, it appears that the application by the Claimant cannot be granted. When this matter came before Shanks J. on February 32007 it was adjourned pending receipt of the written submissions on that assessment by the Defendant’s Counsel. rd, 2005 the parties reported to the Court that they had reached agreement. Counsel for both sides undertook to lodge an agreed Order. The agreed Order was never lodged.

[3]The matter came up before Shanks J. on June 22nd, 2005. Realizing that no order had been lodged, the Judge reduced the agreement of the parties to a Court Order which the Court Office produced. Under that Order the Defendant was to carry out certain works.

[4]The Claimant considered that the works were not carried out in accordance with the Court Order and applied to have the Defendant committed for contempt. Eventually the works were completed and the Court appointed engineer has certified that the works conform to the Order of the Court.

[5]The Claimant now applies to have his damages assessed. Unfortunately there has never been any judgment entered for the Claimant for damages to be assessed.

[6]The Claimant’s application is thus dismissed as wholly misconceived.

[7]I award the Defendant his costs on this application which I assess in the amount of $750.00. _________________________ BRIAN S. COTTLE HIGH COURT JUDGE

Processing runs
RunStartedStatusMethodParagraphs
16929 2026-06-21 17:57:39.367772+00 ok pymupdf_layout_text 8
7590 2026-06-21 08:20:22.846636+00 ok pymupdf_text 22